Working time: 10 hours; Feeding material: limestone, below 30mm; Output size: 0-3.5mm. Main equipment: VSI5X1145 sand making machine(1 set), 2Y2160 vibrating screen (1 set), etc.
Working time: 20 hours; Feeding material: granite, below 10mm; Output size: 0-4mm. Main equipment: VSI5X9532 sand making machine (1 set), 2Y2160 vibrating screen (1 set).
Working time: 14 hours Feeding material: cobblestone Output size: 0-5mm Main equipment: PE600*900 jaw crusher (1 set), CS160 cone crusher (1 set), VSI1140 impact crusher (2 sets).
Working time: 9 hours; Feeding material: 0-10mm dry limestone, containing a small amount of clay powder; Output: fineness modulus 2.7 fine sand, which contains 6% powder content; dry limestone powder.
Daily operation: 15 hours; Feeding material: limestone chips (5-10mm); Final product: ordinary dry-mixed mortar, masonry mortar, plastering mortar and ground mortar
Application: mainly for infrastructure use of a country in Southeast Asia. the capacity is 1000-1200t per hour.
Application: main supply of local mixing station, export Taiwan, etc. the capacity is 500-600 tons.
Application: mainly supply for the maintenance of Xijiang River Hydropower Station construction.
Product application: Daozhou - Hezhou expressway and Hezhou large concrete mixing station.
Product application: Shanghai - Kunming high-speed rail and local large mixing station. the capacity is 350 tons per hour of gravel, 150 tons of fine sand.
Product application: ceramic raw materials. production line capacity is 250 tons per hour.
Concrete aggregate 3000 tons per day(0-5-10-30mm), including the fine mechanism sand 1000 tons. Application: Dalian scenic area infrastructure projects.
Product application: dry-mixed mortar. production line production capacity is 70 tons per hour of sand mortar.
Application: highway, high-speed railway, mixing station. the capacity is 60-70t per hour, gravel production capacity is 70t per hour.
Concrete aggregate 3000 tons per day (0-5-10-15-30-70mm). Application: Jinan - Qingdao, Binlaiexpressway infrastructure projects.
Product application: cement plant materials and mixing station high standard concrete materials. each production line capacity is 150 tons per hour fine mechanism sand, 50 tons gravel particles (5-10-20-30mm).
Application: mainly for BaoLan High-speed rail Project Construction. 100 tons per hour.
This customer bought our centrifugal impact sand-making machine to replace roll crushers. Application: Dry-mixed mortar.
Product application: supply high-speed rail, Gezhouba Hydropower Station. 150-250 tons per hour.
Product application: local large concrete mixing station.
Product Application: Road cushion, home mixing station and local brick enterprises.
Finished Product Size: 0-15mm,15-25mm HJ98 high-efficiency jaw crusher CS160 cone crusher
The most advanced K Series Mobile Crushing Station is flexible. Compare with fixed production line with respect to investment costs, it is recommendable for lower cost.
With the rapid growth of world economy, every country starts to focus on the infrastructure construction. To adapt for the modernization of infrastructure, the demand for aggregate
Working time: 20 hours; Feeding material: granite, below 700mm; Output size: 10-30mm, 5-10mm, 0-5mm. Main equipment: PE900*1200 jaw crusher (1 set), CS240 cone crusher (1 set), HPC220 cone crusher (2 sets), etc.
Woking time: 16 hours; Feeding material: granite, 0-800mm; Output size: 0-3, 3-5, 5-10, 10-31.5mm. HJ98 jaw crusher, HPT300 multi cylinder hydraulic cone crusher and VSI5X8522 centrifugal impact crusher
Working time: 15 hours; Feeding material: Granite; Output size: 36-46-56-68mm and 0-5-16-35mm. the host uses HJ110 jaw crusher and HPT300 multi cylinder hydraulic cone crusher
Working time: 8 hour; Feeding material: limestone, 700mm below; Output size: 10-31.5mm, 5-10mm, 0-5mm. Main equipment: PE1000*1200 jaw crusher (1 set), PFW1315III impact crusher (2 sets). etc.
Working time: 7 hour; Feeding material: pebbles, below 300mm; Output size: 0-4mm sand, 10-30mm stone. Main equipment: PE500*750 jaw crusher (1 set), HPC220 cone crusher (1 set), VSI5X1145 sand making machine (1 set), etc.
Working time: 7-8 hours; Feeding material: pebbles, ≤150mm; Output size: 15-30mm stone, mechanism sand ≤5mm.Main equipment: HPC220 cone crusher (1 set), VSI5X9532 sand making machine (1 set), etc.
Working time: 8 hour; Feeding material: pebble,100-300mm; Output size: 5-20mm stones, ≤5mm mixed sand. Main equipment: PE500*750 jaw crusher (1 set), HPC220 cone crusher (1 set), VSI9526 sand making machine (1 set), etc.
Designed, manufactured and installed by SBM, this VU120 machine-made sand production line in Shijiazhuang was put into use in February, 2015. Its establishment plays an important role in relieving shortage of natural sand, protecting environment and devel
The 4.0 industry is a high-tech strategic plan proposed by the government of Germany, the corresponding concept in China is "made in China 2025", the Ministry of industry and Chinese Academy of engineering define Chinese version of industry 4.0 core obj
Limited by the policies, the supply of natural sand is decreasing sharply while the traditional machine-made sand has some weaknesses like big fine modulus, low yield and severe dust pollution. Foe Hunan a huge potential market, the advanced, eco-friendly
Sri Lanka 50TPH Hard Material Crushing Line
Thailand 80-100 Calcite Crushing Line
Myanmar 120TPH Granite Crushing Line
Myanmar 150TPH Granite Crushing Line
Myanmar 180TPH Granite Crushing Line
Russia 200TPH Pebble Crushing Line
Mongolia 200TPH Granite Crushing Line
Mongolia 240TPH Granite Crushing Line
Indonesia 350TPH Gold Ore Crushing Line
Thailand 1000TPH Iron Ore Crushing Line
Tailing &Construction Waste Crushing Basic IntroductionMaterial: Tailings and building wastesFinished Product: Dry-mixed mortar, high-quality aggregate and vari
Design SchemeMaterial: GraniteFinished Product: High-quality aggregateCapacity: 500TPHOutput Size: 0-5-10-31.5-65mmGranite Crushing Project BackgroundAt the end
Tuff Crushing Design SchemeMaterial: TuffFinished Product : Gravel, high-quality sandOutput Size : 0-5-15-20-38mmCapacity : 1500 -1800TPHApplication : Building
Limestone Sand-making Design SchemeMaterial: LimestoneOutput Size: 0-5mm, 5-10mm, 10-20mm, 20-31.5mmApplication: Infrastructure construction like railway, road
This project is located in Sichuan, China. Because the local area is in short supply of natural sand but abundant in pebbles, our customer decided to invest peb
Application: The finished products are used in road, mixing plant and local brick production.Equipment: K Series Wheel-type Mobile Crushing StationBuilding Wast
Limestone Tailing Crushing Project ProfileThe amount of natural sand is decreasing. And because of government’s limitation on sand quarrying, the advanced and
Limestone Crushing Design SchemeUnder the premise of meeting customer’s demand on quality of products, environment protection and flexible production, SBM equi
The main machines of this production line are from SBM. It is the first line that sand-making machines are installed on the ship. The production line is mainly
Pebble Crushing Design SchemeProject Site: Hangzhou, ZhejiangOutput Size: 0-5mm, 5-10mm, 10-31.5mmMaterial: PebbleEquipment: PE Series Jaw Crusher, CS Series Sp
Tailing Crushing Design SchemeDaily operation: 12hMaterial: TailingFinished Product: High-quality machine-made sand (0-5mm)Tailing Crushing Project ProfileThe p
Construction Waste Crushing Design SchemeProject Site: Fujian, ChinaCustomer: A resource recycling companyEquipment: K Series Mobile Crushing StationMaterial: C
Coal Gangue Crushing Design SchemeMaterial: Coal gangueCapacity:250-300Tons/HourEquipment: Dual-drive track-type mobile crushing stationApplication: The finishe